Question 1 of 10
? Which of the following is not a PMBOK Knowledge Area
Procurement management 1-
Integration management-
Execution management -
Communications management -
Question 2 of 10
A project manager has been asked to manage a research project. Typically, research projects are not clearly defined and involve a lot of uncertainty. What phase-to-phase relationship should the project manager use for this project?
Open-ended relationship-
Iterative relationship-
Overlapping relationship-
Sequential relationship-
question 3 of 10
The transition from one phase to another within a project's life cycle (e.g., from design to manufacturing) is typically marked by:
Kill point-
Monte Carlo-
Constraint-
Decision tree-
Question 4 of 10
Ongoing operations and a project both have Initiating Processes, but only a project has __________.
Planning Processes-
Closing Processes.-
Controlling Processes-
Executing Processes-